Mira Costa College HUB Server


1 2 3

The project scope included the addition and replacement of cooling for an existing 1,000 square foot data center providing support for Mira Costa College's Campus. The data center houses 15 server racks and is cooled by two new, redundant 15 ton in-row, precision computer units utilizing hot aisle, cold aisle containment.

Design Features

  • 30 tonsĀ  of cooling
  • Controls integration into existing BMS
  • Humidity control
Divider